1. Advise builder of damper
location and direction of airflow.
2.
Damper should be laid on a 3mm to 4mm thick mortar bed to ensure
airtight seal. Intumescent slats shall be in the VERTICAL position.
NOTE: "AIRFLOW" direction is optional.
3.
Complete brickwork around and over the damper, filling gap between
brickwork and damper with a thin layer of mortar.
4.
Connect ductwork to fire damper using fire rated mastic to fill
recess if using raw edge connection, or apply mastic to both surfaces of
the TDF flange connections. (Bolts must be of a low melting point
material.)
|