1. INITIAL DAMPER TEST -
Before installing Damper into concrete slab, check damper's closing operation.
This can be achieved by placing damper into it's installation position. Hold
blade stack whilst removing UL33 rated fusible link. Holding the blade
stack even with both hands release blades to allow closure. After
viewing proper operation gather up blade and refit the UL33 fusible link to its
original position.
2.
Ensure slab penetration is to the AS/NZS-1682.2 requirements.
3.
Apply fire rated mastic to the slab surface that the fire damper flanges
sit flush upon, to ensure an airtight seal.
4.
Lower the damper into position, sitting the flanges on the fire rated
mastic.
5.
With the steel clamp plates provided, follow the installation diagram
below. Refer to note below for clamp plate quantities.
6.
With installation complete to the installation details, repeat INITIAL DAMPER TEST as described in point
#1 to check the dampers blade closing performance before connecting the
ductwork or grilles if required to AS4254 standards.
7.
Connect ductwork to fire damper using fire resistant mastic to fill
recess if using raw edge connection, or apply mastic to both surfaces of
the TDF/TDC flange connections. (bolts must be of a low melting point
material.)
|